Nepal's Public Procurement Act, 2063 - the law that governs every government tender, contract, and construction project - has just been revised in a major way through the Public Procurement (Second Amendment) Ordinance/Bill, 2083. This is the first big overhaul in about 20 years, and it directly changes how site engineers, consultants, contractors, and government engineering offices work day to day. This guide collects every important point of the revision, explained in plain language with engineer-focused examples.
1. Expanded Definitions and Scope
2. Pre-Procurement Preparation (site and budget readiness)
3. New Procurement Methods (Reverse Auction, E-Marketplace)
4. Bidding Procedure and Timeline Changes
5. Bid Evaluation and Low Bidding Rules
6. Contract Management and Execution (variation orders, advance, JV, termination)
7. Institutional and Administrative Changes
8. Process Flow and Quick Revision Table
1. Expanded Definitions and Scope
- Public Entity: Now clearly includes "Projects" (aayojana), not just government offices and departments
- Goods: Now explicitly includes intangible (non-physical) items, not just physical goods
- Other Services: Expanded to include security services, cleaning, air ticketing, advertisement, and infrastructure management/operation and maintenance work
- Domestic Goods: New definition - a product qualifies as domestic only if it uses Nepali labor and raw materials, or has at least 30 percent value addition done inside Nepal
2. Pre-Procurement Preparation is Now Compulsory
Before any tender can even be published, the concerned office must complete this "homework":
- Budget must be confirmed (for multi-year contracts, at least the first year's budget plus a clear funding source for the remaining years)
- Construction site must be ready - land handed over, compensation paid, trees or old structures cleared
- Environmental study report (IEE/EIA), where required, must already be approved
3. New Procurement Methods
3.1 Reverse Auction (new method, listed as method 11)
Bidders compete by lowering their price within a fixed time window. The approved cost estimate acts as the ceiling price - no one can bid above it.
3.2 Government E-Marketplace (Section 41ka)
A new online system lets public offices directly buy listed goods and services, up to a prescribed limit, without running a full tender process - like an official government "online store" for routine purchases.
4. Bidding Procedure and Timeline Changes
| Notice Type | Old Rule (2063 Act) | New Rule (2083 Amendment) |
|---|---|---|
| National bids | 30 days | 21 days |
| International bids | 45 days | 30 days |
| Re-invitation (1st) - national | Longer period | 7 days |
| Re-invitation (1st) - international | Longer period | 15 days |
| Short/urgent notice | 7 days | 3 days |
- Electronic priority: If bids are invited electronically, the office no longer needs to also publish in newspapers or other media
- Two-envelope system: Now clearly mandatory for construction works above a certain value and for complex goods/services - technical proposal is evaluated first, financial (price) proposal is opened only after technical qualification
5. Bid Evaluation and Low-Bid Handling
- Bid Capacity: Now explicitly recognized as a legal basis to check a bidder's technical and financial capability
- Extreme low bids: If a construction bid is more than 30 percent below the cost estimate, the evaluation committee must demand a detailed rate analysis; if the analysis shows the work cannot realistically be done at that rate using standard norms, the bid must be disqualified
- Negotiation: If the lowest bid is significantly higher than the cost estimate, the office can negotiate a lump-sum discount with that bidder, as long as specification and quality are not compromised
- Tie-break: If two or more bidders quote the exact same lowest price, the winner is now chosen by lottery
6. Contract Management and Execution
6.1 Mobilization Advance
Capped at 20 percent of the contract value, covering things like labor camp setup, machinery arrangement, and site preparation. The contractor must now first submit a schedule of main activities before the advance is released.
6.2 Variation Order Approval Authority
New percentage-based limits decide who can approve a variation (change) order:
Also important: construction work cannot be halted just because of a dispute between the contracting parties - the project must continue while the dispute is resolved separately.
6.3 Joint Venture (JV) Responsibility
All members of a joint venture now bear full liability for the project together - responsibility cannot be pushed onto just one JV partner.
6.4 Contract Termination
If a contract is terminated because the contractor defaulted, any additional cost the government has to pay to get the work completed by someone else will be recovered from the defaulting contractor as government dues.
7. Institutional and Administrative Changes
- Departmental action: Officials who cause delays - for example by not providing site clearance on time, delaying designs, or not releasing payments on time - can now face departmental action
- Incentives: Contractors and consultants who complete quality work ahead of schedule can get a bonus or an official letter of appreciation; procurement staff can also be rewarded for timely, quality work
- Government Procurement Service Office: A brand-new office created under the Office of the Prime Minister to help public entities with supplier selection and smooth procurement
8. How a Procurement Now Flows (Engineer's View)
Quick Revision Table (for Loksewa candidates)
| Old Act | Public Procurement Act, 2063 |
|---|---|
| New Change | Public Procurement (Second Amendment) Ordinance/Bill, 2083 |
| Public Entity now includes | Projects (aayojana) |
| Domestic goods rule | At least 30 percent value addition in Nepal |
| New bidding method | Reverse Auction (method 11) |
| New buying system | Government E-Marketplace, Section 41ka |
| National notice period | 30 days reduced to 21 days |
| International notice period | 45 days reduced to 30 days |
| Urgent/short notice | 7 days reduced to 3 days |
| Low bid check | More than 30 percent below estimate needs rate analysis |
| Tie-break method | Lottery |
| Mobilization advance | Up to 20 percent, needs activity schedule first |
| Variation order (5/10/15/above 15 percent) | Gazetted 3rd / 2nd / 1st Class / Department Head |
| JV liability | All partners fully liable, not just one |
| New office created | Government Procurement Service Office |

0 Comments
How it was ?, Please comment